Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_01.jpeg
1. The tank ring beam is in-filled with concrete or compacted sand to within 200-300mm of the top of the beam, a RAWSEAL® TR35 fillet is bedded in Rawpaste Mastic at the 90° angle around the circumference of the tank.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_02.jpeg
2. The RAWMAT® HDB membrane is laid across the concrete/sand floor within the ring beam.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_03.jpeg
3. The rolls of RAWMAT® HDB are laid and overlapped following the lap lines marked on the rolls.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_04.jpeg
4. The tank base is covered fully with the RAWMAT® HDB membrane and sealed to the ring beam.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_06.jpeg
5. Once sealed to the tell-tale an additional patch of RAWMAT® HDB is sealed to pipe and the main sheet of RAWMAT® HDB then sealed further with Rawpaste mastic.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_07.jpeg
6. The sealed pipe provides protection against uncontrolled leakage at the pipes.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_08.jpeg
7. The 150mm overlaps between the sheets are sealed by the application of Rawpaste Mastic to the black geotextile before sealing the joint.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_09.jpeg
8. Once all overlaps have been sealed and tell-tales secured the tank base is ready for the placement of the backfill.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_10.jpeg
9. 200-300mm of compacted sand is placed over the RAWMAT® HDB membrane prior to the placement of the bitsand layer and the tank base plate.
-
Concrete Ring Beams
../media/content/petrochemical_lining_product_applications/concrete_ring_beams/slideshow_large/Concrete_Ring_11.jpeg
10. Bitsand layer placed awaiting placement of tank.